The S38 Adoption Process

Key Build Stage 6 Footpaths

illustration-4
Footpaths checksEvidenceFrequency
Verification of materials for sub-base material (confirmation non-frost susceptibility), binder course and surface course. Tickets All sources
Inspection of formation (clear of vegetation/topsoil). Visual All lengths
Weed spray to formation. Visual All lengths
Inspection of all backfilling and compaction of all service trenches, redundant land drainage (with sub-base material). Visual All lengths
Checks on depth of sub-base. Visual All lengths
Inspection of edgings, including bed/backing and line and level (ensure line of edgings are dropped at vehicular crossings). Visual All lengths
Check for dropped kerbs and tactile crossing, ensure dropped kerbs do not exceed 6mm up stand. Visual All locations
Ensure sufficient depth is provided to allow for 25mm of surface course. Visual All lengths
Ensure street lighting columns are installed in the correct location and within adoptable area. Significant defects (such as damaged columns) are rectified. Visual All columns
Cores to separately assess thickness, compaction and bond of binder and surface course layers. Testing One per 100m (minimum three per site)