As the final step in the Section 38 adoption process, the developer shall submit as-built information to verify that the works have been completed in accordance with the approved design and specification.
In preparation for us to accept the finished roads and footpaths, an on-site survey shall be carried out, and the results with actual coordinates and finished levels as a layout drawing, known as an as-built drawing, shall be submitted to, and approved by, us.
As-built drawings should be provided at a scale of 1:500 at A1, orientated to National Grid North and in Portable Document Format (PDF). A minimum of three drawings described below shall be required.
This drawing shall be titled ‘Road and Footpath As-Built’, should have an appropriate key and include the following:
This drawing shall be titled ‘Drainage As-Built’, should have an appropriate key and include the following:
Details of components such as flow control devices and specialist materials shall be provided.
This drawing shall be titled ‘Landscaping As-Built’, should have an appropriate key and include the following: